70-348 Dumps | Cost resources affect the schedule

Question : 7

Cost resources affect the schedule when they’re assigned to tasks. Review the underlined text. If it makes the statement correct, select “No change is needed”. If the statement is incorrect, select the answer choice that makes the statement correct.

A. No change is needed.
B. Work resources.
C. Material resources.
D. Budget work resources.

Answer: B

70-348 Dumps | Your organization is in the process

Question: 6

Your organization is in the process of implementing Microsoft PPM. You need to configure Microsoft PPM to ensure that project managers can choose the tracking method for each of their projects. On the Task Settings and Display page, what should you do?

A. Set the tracking method to Free form
B. Select the check box Force project managers to use the progress reporting method specified
above for all projects.
C. Clear the check box Force project managers to use the progress reporting method specified above
for all projects
D. Set the tracking method to Percent of work complete

Answer: A

70-348 Dumps | You are project manager for an

Question: 5

You are project manager for an organization that is uses Microsoft PPM. You need to create a project deliverable for the current project. What should you do?

A. In Microsoft Project, manage a deliverable.
B. On the project site, edit the list to include the Task ID attribute.
C. In Microsoft Project, use Sync Deliverables.
D. On the project site, create a new item in the Deliverables list.

Answer: D

70-348 | You are a project manager in an organization…

Question: 4

You are a project manager in an organization that is using Microsoft PPM. You are managing a 12-month project Resources have been working on the project for six months. You need to determine how the project is tracking against the initial goals in terms of duration, work and cost. Which three actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area, and arrange them in the correct order:

70-348 exam dumps

 

Answer:

70-348 | You are the Microsoft PPM administrator for a large…

Question: 3

You are the Microsoft PPM administrator for a large company. The IT manager uses four business drivers for prioritization. The priority of all four drivers is set at 25 percent. The IT manager adds an additional business driver that has a priority value set to 30 percent You need to create a new prioritization that includes the additional business driver. What should you do?

A. Create a new calculated prioritization. Select the drivers to priority.
B. Create a new manual prioritization. Select the correct department, and then select the drivers to prioritize.
C. Create a new manual prioritization. Select the drivers to prioritize, enter the value for each dnver, and then choose to normalize.
D. Create a new manual prioritization. Select the drivers to prioritize, and then rank the drivers sequentially.

Answer: A

70-348 | An organization uses Microsoft PPM to manage projects…

Question: 2

An organization uses Microsoft PPM to manage projects. The organization tracks all projects by collecting time on tasks on a daily basis. You need to ensure that resources can enter their time on tasks.
Which three actions should you take? Each correct answer presents part of the solution.

A. On the Task Settings and Display page, set the tracking method to Hours of work done per period
B. On the Task Settings and Display page, select Resources should report their hours worked per day
C. On the Task Settings and Display page, clear the check box Force project managers to use the progress reporting method specified above for all projects.
D. On the Task Settings and Display page, select the check box Force project managers to use the progress reporting method specified above for all projects.
E. Instruct the project managers to select the tracking method for their project in Microsoft PPM.

Answer: A,C,D

70-348 | You use Microsoft PPM to manage an e-commerce portal…

Question: 1

You use Microsoft PPM to manage an e-commerce portal development program. The program is separated into individual projects that represent each area of development. This allows each group to manage its own tasks while still having progress visibility at the program level. You need to be able to see all programs and their associated individual projects from within Project Center. What should you do?

A. Select the Enterprise Project Type Name field as the value for grouping.
B. Select the Master Program field as the value for filtering.
C. Select the Subprojects check box.
D. Select the Project Details view.

Answer: C