Question : 16

You are a project manager who uses Project Professional 2013. Two of your resources job share; Resource1 works Monday, Tuesday, and a half day Wednesday. Resource2 works the remaining work week. You need to set up their calendars to reflect the job-sharing arrangement. What should you do?

A. Open each resource and set a recurring exception to reflect the non-working days.
B. Open each resource and amend the working time on each resource’s calendar.
C. Open each resource and set their Resource Availability units to 50%.
D. Open each resource and use the Resource information dialog box to create a new calendar. Change the Default Work Week to reflect the working time.

Answer : B